Progress
August 31, 2026
Concrete foundation work progressed steadily throughout August and remains on track for completion. The exposed colored and board‑formed concrete walls have been installed, and the cleaning method for these colored walls has been tested, reviewed, and approved by the design team.
Key concrete placements moved forward as scheduled, including the first slab on grade in the northwest corner on August 12 and the concrete wall separating the sallyport from secure parking on August 14. Installation of Concrete Masonry Unit (CMU) walls on the main level were installed with all walls observed to be properly reinforced and fully grouted.
Additional site work continues with waterproofing installation on completed foundation walls and ongoing subgrade electrical and mechanical rough‑in efforts. Electrical transformers were installed in July, and the necessary rough‑in and connections completed in August.