Budget
The total project budget is $118,500,000, which includes all soft costs and contingencies.
Budget update (10/16/2025)
Courthouse Construction Project is currently 5% under budget after Phase 1 completion
Funding
- Teton County reserved $30,000,000 in General Funds for the Justice Center project
- In 2024, Teton County voters approved an $88,000,000 Specific Purpose Excise Tax
- SPET collections began in April 2025
- Approximately $21-$22 million is raised each year through SPET
- If tax revenue collection rates remain constant, it will take approximately
4 to 4.5 years to acquire $88,000,000 (2029)