Progress

August 31, 2026

Concrete foundation work progressed steadily throughout August and remains on track for completion. The exposed colored and board‑formed concrete walls have been installed, and the cleaning method for these colored walls has been tested, reviewed, and approved by the design team.
Key concrete placements moved forward as scheduled, including the first slab on grade in the northwest corner on August 12 and the concrete wall separating the sallyport from secure parking on August 14. Installation of Concrete Masonry Unit (CMU) walls on the main level were installed with all walls observed to be properly reinforced and fully grouted.
Additional site work continues with waterproofing installation on completed foundation walls and ongoing subgrade electrical and mechanical rough‑in efforts. Electrical transformers were installed in July, and the necessary rough‑in and connections completed in August.

Photos

August 31, 2026

May 13, 2026

April 15, 2026

April 7, 2026

March 25, 2026

March 12, 2026

February 20, 2026

Videos

Visuals